Question: Given the task setrin table 1 Task TI T2 13 Execution time, C 1 2 3 Period. T 2 6 8 Verify the schedulability
Given the task setrin table 1 Task TI T2 13 Execution time, C 1 2 3 Period. T 2 6 8 Verify the schedulability of the task set in table 1 under EDF and draw the schedule timeline. Show all the necessary workings. (3 Marks)
Step by Step Solution
3.46 Rating (172 Votes )
There are 3 Steps involved in it
Verifying Schedulability of Task Set under EDF Task Set Task Execution Time C Period T T1 2 T2 T2 6 ... View full answer