Question: Given the task times listed above, what I the minimum cycle time that can be achieved by a line? What is the maximum daily output
- Given the task times listed above, what I the minimum cycle time that can be achieved by a line? What is the maximum daily output that could be achieved by a single line?
- b)What is the takt time for each line? What is the theoretical minimum number of workstations needed on each line?
Minimum Cycle Time: 3 Minutes Maximum Daily Output: 160 Returns
c) Make workstations assignment using the largest eligible task rule. Calculate the cycle time, idle time, percent idle time and efficiency delay for the resulting line.