Question: Given the tasks, estimated durations, and crash costs shown below, what would be the minimum cost to reduce the project by 1 day? A .

Given the tasks, estimated durations, and crash costs shown below, what would be the minimum cost to reduce the project by 1 day?
A. $200
B. $500
c. $700
D. $800
E. $1000