Given the time-phased work packages and network, complete the baseline budget form for the project. What is the cumulative budget at the 9th time period?
\table[[Soccer Toy Project Cost By Week ,,,,,],[,1,2,3,4,5],[A Design prototype,10,8,6,0,0],[B Build prototype,4,10,0,0,0],[C Order parts,5,5,10,0,0],[D Prepare production,12,8,4,16,0],[E Prepare marketing,6,6,0,6,12],[F Assemble and test,18,18,0,0,0],[G Launch,12,0,0,0,0]]
Answer Choices:
142
112
125
116
 Given the time-phased work packages and network, complete the baseline budget