Question: Given the time-phased work packages and network, complete the baseline budget for the project. 6 9 WP Design WP Survey WP Report 7 6 6

Given the time-phased work packages and network,

Given the time-phased work packages and network, complete the baseline budget for the project. 6 9 WP Design WP Survey WP Report 7 6 6 7 9 9 9 7 8 6 Project Network 0 1 3 3 2 3 0 Design Survey Report 0 33 6 3 Note: Leave no blanks for answers: enter 0 (the digit, not the letter) where necessary. Time-phased budget ($ 000) Week Task Budget Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 22 7 6 6 9 Design Survey Report Total 47 20 89 Cumulative