Question: Given the two projects with given cash flows, the NPV of project A is how many more (or less use the negative sign if less)

Given the two projects with given cash flows, the NPV of project A is how many more (or less use the negative sign if less) dollars than project B if the discount rate is 9%? Answer with two decimals. Project A Project B CF0: -11,685 CF1: 3,293 CF2: 4,654 CF3: 9,863 CF4: 9,151 CF5: 2,103 CF0: -11,685 -10,729 CF1: 3,293 1,820 CF2: 4,654 2,085 CF3: 9,863 5,313 CF4: 10,134 8,538 CF5: 2,103 13,852