Question: Given the WBS , what is the earliest start for activity D ? table [ [ Activity ( WBS ) , Immediate,Activity Time ]

Given the WBS, what is the earliest start for activity D?
\table[[Activity (WBS),Immediate,Activity Time],[,Predecessors,(weeks)],[Start,None,0],[A.Kickoff Meeting,Start,3],[B.Select administrative staff,A,5],[C.Select system configuration,B,2],[\table[[D.Select Sonar option],[E.Create technical data]],B,17],[package,B,C,D,4],[F. Evaluate parts options,C,5],[G. Decide on parts,D,7],[H. Inform client of parts,E,F,G,3],[selection,F,H,14]]
5
25
22
8
 Given the WBS, what is the earliest start for activity D?