Question: Given the work element times shown in the following table, what is the theoretical minimum number of workstations ? Round your answer UP to the
Given the work element times shown in the following table, what is the theoretical minimum number of workstations? Round your answer UP to the nearest whole number.
| Work Element | Time (Sec) | Immediate Predecessor(s) |
|---|---|---|
| A | 21 | None |
| B | 41 | A |
| C | 24 | A |
| D | 37 | B |
| E | 34 | B |
| F | 31 | C |
| G | 34 | C |
| H | 25 | D, E |
| I | 38 | F, G |
| J | 47 | H, I |