Question: Given this information on planned and actual inputs and outputs for a service center, determine the work backlog for each period. The beginning backlog is

Given this information on planned and actual
Given this information on planned and actual inputs and outputs for a service center, determine the work backlog for each period. The beginning backlog is 12 hours of work. The figures shown are standard hours of work, Input Planned Actual Period 3 24 20 2 24 27 24 25 4 24 22 5 20 24 Output Planned Actual 1 24 24 2 24 22 Period 3 24 23 4 24 24 5 23 24 Click here for the Excel Data File Backlog Period 1 2 3 4 5