Question: Glenda, a project manager for a new construction project, is working on a project schedule management plan. What is the correct order of processes that
Glenda, a project manager for a new construction project, is working on a project schedule management plan. What is the correct order of processes that she needs to follow in order to arrive at an appropriate schedule management plan?
Group of answer choices
Define activities, Estimate activity resources, Estimate activity durations, Sequence activities
Define activities, Sequence activities, and Estimate activity durations
Define activities, Estimate activity resources, Sequence activities, Estimate activity durations
Define activities, Estimate activity durations, Estimate activity resources, Develop schedule