Question: good morning I need this answer with all full work thanks Question 1.9 (10 Points): Complete the Projected On Hand Inventory Row. Week 1 Week
good morning I need this answer with all full work thanks
Question 1.9 (10 Points): Complete the Projected On Hand Inventory Row. Week 1 Week 2 Week 3 Week 4 15 40 40 50 Finished Product A Gross Requirements Schedule Receipts Planned Deliveries Projected On Hand Inventory Planned Order Releases 25 40 25 Reorder Quantity = 40 Units; Lead Time = 2 Weeks; Safety Stock = 10 Units Answer 1.9 Week 1 Week 2 Week 3 Week 4 r_7