Question: Good project management practice suggests a need to include a within the cost baseline in order to cover identified risks that are accepted, and for
Good project management practice suggests a need to include a within the cost baseline in order to cover identified risks that are accepted, and for which responses have been developed.
Contingency reserve
Project buffer
Control account
Management reserve