Question: Green Builders is currently using the Dual Rate method for overhead allocation. The companys 2014 income statement and the University View project direct cost estimation
Green Builders is currently using the Dual Rate method for overhead allocation. The companys 2014 income statement and the University View project direct cost estimation are given below.
a. As the project manager of University View, how much overhead should you charge on the total project cost?
b. If you switch a single rate method, how much overhead should you charge on the project?