Question: GuruJi Inc is considering different projects for the next year in order to increase its capacity by at least 100,000 units. It has an option
GuruJi Inc is considering different projects for the next year in order to increase its capacity by at least 100,000 units. It has an option to choose between six different projects. The NPVs and capacities for different projects are given below:
| Project | NPV (in $) | Capacity (units) |
| 1 | 100,000 | 10,000 |
| 2 | 300,000 | 40,000 |
| 3 | 250,000 | 50,000 |
| 4 | 200,000 | 25,000 |
| 5 | 350,000 | 30,000 |
| 6 | 100,000 | 15,000 |
Also, the following conditions must be met:
At least one project from 1, 2, and 3 must be selected.
At least one project from 4, 5, and 6 must be selected.
If 1 and 2 are selected then 3 cannot be selected
If 2 is selected then 5 cannot be selected.
If 4 is selected then 6 must be selected and vice versa.
Formulate an integer linear programming problem clearly defining the variables to maximize the NPV.
Use Solver to find the optimal solution.
Which projects should they select?
What is the expected NPV?