Question: H (35 Points) M N 0 P a Assuming that all machines capacity are 1000 hour & consider the following part-machine indicator matrix (the processing
H (35 Points) M N 0 P a Assuming that all machines capacity are 1000 hour & consider the following part-machine indicator matrix (the processing time in hr/part is shown). 1 2 3 4 5 6 7 8 R-> 600 475 250 625 375 700 575 350 A 0.44 0.72 0.57 B 0.41 0.33 0.63 0.62 0.52 0.5 0.3 0.52 0.52 0.47 D 0.25 E 0.51 0.4 0.61 0.35 0.47 F 0.53 0.28 0.37 [15 points) a. Determine the machine groups and the corresponding part families using the DCA algorithm. is points) b. Do conflicts exist? If yes, propose an alternative approach for resolving them. (15 Points) c. Using Straight-Line technique, what would be the optimum sequence of machines in each cell