Question: H Problem 5 Direct labor Standard corkscrew 0.10 Deluxe corkscrew 0.30 Machine time Standard corkscrew Deluxe corkscrew 0.20 0.40 Direct labor Machine time 1 K
WAl uses two resources for each product that it builds: direct labor and machine time. From historical records, WAl calculates the following planning factors: Direct labor for standard corkscrew is 0.10 hour. Direct labor for deluxe corkscrew is 0.30 hour. Machine time for standard corkscrew is 0.20 hour. Machine time for deluxe corkscrew is 0.40 hour. Calculate the capacity needed for the MPS developed in Problem 4