Question: Haft Construction Co. has consistently used the input method based on costs incurred to measure progress toward completion of the project. On January 10, Year
Haft Construction Co. has consistently used the input method based on costs incurred to measure progress toward completion of the project. On January 10, Year 3, Haft began work on a $3 million construction contract. At the inception date, the estimated cost of construction was $2,250,000. The following data relate to the progress of the contract:
| Gross profit recognized at 12/31/Yr 3 | $ 300,000 |
| Costs incurred 1/10/Yr 3 through 12/31/Yr 4 | 1,800,000 |
| Estimated cost to complete at 12/31/Yr 4 | 600,000 |
In its income statement for the year ended December 31, Year 4, what amount of gross profit should Haft report?
$450,000
$300,000
$262,500
$150,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
