Question: Halfway through a project, it becomes clear that the project is behind schedule and is busy overspending. The reason for these failures is that the
Halfway through a project, it becomes clear that the project is behind schedule and is busy overspending. The reason for these failures is that the original estimates were not accurate. Who has the PRIMARY RESPONSIBILITY to solve this problem?
a
The project sponsor
b
Project manager
c
All stakeholders
d
All project team members
e
The person who did the original estimates
f
The person to whom the project manager reports