Question: Halfway through project execution, stakeholders ask for equipment that was expected to be procured I ho project manager explains that: the equipment was purchased, but
Halfway through project execution, stakeholders ask for equipment that was expected to be procured I ho project manager explains that: the equipment was purchased, but differs from what the stakeholders are currently asking for This is because the initial requrements were changed dunng a previous meeting What should the project manager have done to avoid this situation? Ensured changing stakeholder needs and requests were properly mortored Ensured that communications were sent to all stakeholders when requirements change Ensured procurement contracts were able be canceled when situations like this arse Ensured project requirements were validated and communicated with the procurement team
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts