Question: Hardhat Construction Company has a contract to construct a 4,500,000 bridge at an estimated cost of 4,556,250. The contract is to start in July 2019,
Hardhat Construction Company has a contract to construct a 4,500,000 bridge at an estimated cost of 4,556,250. The contract is to start in July 2019, and the bridge is to be completed in October 2021. The following data pertain to the construction period. 2019 2020 2021 Cost to date $1,000,000 $ 2,916,000 $4,556,250 Estimated cost to complete 3,000,000 $ 1,640,250 Progress billing during the year 900,000 2,400,000 1,200.000 Cash collected during the year 750,000 1.750,000 2.000.000 REQUIRED: al Using percentage-of-completion method, prepare schedules to compute the profit and loss to be recognized as a result of this contract for the year ended October 21, 2019, 2020 and 2021, Using cost recovery method, prepare schedules to compute the profit and loss to be recognized as a result of this contract for the year ended October 31, 2019 2020 and 2021
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts