Question: Hardhat Construction Company has a contract to construct a $4,500,000 bridge at an estimated cost of $4,000,000. The contract is to start in July

Hardhat Construction Company has a contract to construct a $4,500,000 bridge at an estimated cost of $4,000,000. The contract is to start in July 2014, and the bridge is to be completed in October 2016. The following data pertain to the construction period. Costs to date 2014 $1,000,000 2015 2016 $2,916,000 $4,050,000 Estimated costs to complete 3,000,000 1,134,000 Progress billings during the year 900,000 2,400,000 1,200,000 Cash collected during the year 750,000 1,750,000 2,000,000 Record the journal entries for 2014, 2015, and 2016 using the percentage of completion method Record the income statement and balance sheet for 2014, 2015, and 2016
Step by Step Solution
There are 3 Steps involved in it
To complete this problem well apply the percentageofcompletion method to track and recognize revenue over the contract period This method is especiall... View full answer
Get step-by-step solutions from verified subject matter experts