Question: Hardy Construction Ltd . Signed a contract to build an office complex for Schtick Corp. for $ 5 . 5 million. Under the terms of
Hardy Construction Ltd Signed a contract to build an office complex for Schtick Corp. for
$ million. Under the terms of that contract, Hardy Construction was given a firm
schedule for completion of the building, and there were financial penalties if they failed
to finish the project on time. Hardy Construction hired Laurel Electric Co as a
subcontractor to install the wiring in the building. The terms of that subcontract
between Hardy Construction and Laurel Electric required Hardy to pay Laurel $
on completion of the wiring and was to include all material and labour. Laurel Electric
started work immediately, but they soon discovered that it had made a mistake and had
underestimated the cost to them of performing the contract. Laurel therefore
approached Hardy Construction and stated that unless it was promised an additional
$ it simply would not be able to complete the job. Hardy Construction realized
that it could not possibly find a replacement for Laurel Electric on short notice and that
any delay in the completion of the project would trigger the penalty clause in its'
contract with Schtick Corp. As a result, Hardy Construction agreed to Laurel Electric's
demand for an additional $ Although Laurel Electric completed its performance
on schedule, Hardy Construction refuses to pay Laurel more than $
a How much does Hardy have to pay to Laurel for the contract? Please explain your
answer fully with reference to the basic elements of a contract for each relevant
contract. marks
b Why might Hardy Construction consider paying the extra money to Laurel even if it
doesn't have to do so legally?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock