Question: Harnesses are the flow unit in a process with two sequential resources. The capacities of the resources are 4 . 2 and 2 . 9

Harnesses are the flow unit in a process with two sequential resources. The capacities of the resources are 4.2 and 2.9 harnesses per second. Demand occurs at the rate 3.8 harnesses per second.
What is the utilization (%) of the first resource?
Note: Round your answer to 1 decimal place.
Utilization
%