Question: Harold is the project manager for a large construction project his company is completing for a client. This project has internal and external stakeholders, including

Harold is the project manager for a large construction project his company is completing for a
client. This project has internal and external stakeholders, including members of the community
who are opposed to the project, although it has been approved by the city. Harold is preparing
to create a stakeholder engagement plan and hes gathering several inputs for the plans
creation. Which one of the following inputs will most help Harold create a strategy for
stakeholder management and engagement?
A. Project Management Plan
B. Stakeholder Register
C. Enterprise Environmental Factors
D. Organizational Process Assets

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!