Question: have yet to get a correct answer Problem 13-3 (Algo) The following table lists the components needed to assemble an end item, lead times (in
have yet to get a correct answer
Problem 13-3 (Algo) The following table lists the components needed to assemble an end item, lead times (in weeks) and quantities on hand, Amount on Hand OK Item End L C Lead Time 1 2 3 4 3 11 17 23 34 25 7 Direct Components L(2), C(1), K(3) B(2), (3) G(2), B(2) H(4), B(2) ences B 3 3 H Click here for the Excel Data File o. If 43 units of the end item are to be assembled, how many additional units of Bare needed? (Hint You don't need to develop an MRP plan.) Additional units