Question: he constraint for resource 1 is 5 X 1 + 4 X 2 100. If X 1 = 10 and X 2 = 5, how

he constraint for resource 1 is 5 X1 + 4 X2 100. If X1 = 10 and X2 = 5, how much of resource 1 is unused?

20

30

40

50