Question: he help me this question plz asap a and b a) Butik Dunia Pengantin has been asked to make five (5) different types of wedding
he
help me this question plz asap a and b
a) Butik Dunia Pengantin has been asked to make five (5) different types of wedding suits for separate customers. The table 3 below highlights the time taken in hours for measuring and cutting then sewing and finishing of each of the suits. Which schedule finishes sooner: First-come, first served following the sequent (A, B, C, D, and E) or a schedule using Johnson's rule? (20 marks) Table 3: Processing Time (hour) Suit Measuring and Cutting (J1) Sewing and Finishing (J2) A 2 4 B 8 7 6 5 D 1 5 E 3 4 b) List and briefly explain five (5) out of eight (8) sources of waste in lean systemsStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock