Question: he Project Manager for a house construction project has been asked to look at alternatives to reduce project duration. As shown on the project network
he Project Manager for a house construction project has been asked to look at alternatives to
reduce project duration. As shown on the project network hereunder, the normal project
duration is months, at a normal cost of $k Crash cost and time data are provided by the
experts in the hereunder table. Indirect costs are $k and reduce by $k for each month
reduction in project duration.
Compute the direct, indirect and total costs for each project duration between normal
time and the maximum time the project can be crashed. Show your calculations for each
of the crash steps what activity, at what direct, indirect and total costs
What is the optimum costtime duration? Whats the project cost at this optimum cost
time duration?
Activity Crash cost Maximum Normal Normal
slopecrashable Time Cost
# of times months$k
A
B
C
D
E
F
Total
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock