Question: he Project Manager for a house construction project has been asked to look at alternatives to reduce project duration. As shown on the project network

he Project Manager for a house construction project has been asked to look at alternatives to
reduce project duration. As shown on the project network hereunder, the normal project
duration is 27 months, at a normal cost of $300k. Crash cost and time data are provided by the
experts in the hereunder table. Indirect costs are $300k, and reduce by $45k for each month
reduction in project duration.
1) Compute the direct, indirect and total costs for each project duration between normal
time and the maximum time the project can be crashed. Show your calculations for each
of the crash steps (what activity, at what direct, indirect and total costs)
2) What is the optimum cost-time duration? Whats the project cost at this optimum cost-
time duration?
Activity Crash cost Maximum Normal Normal
(slope)(crashable) Time Cost
# of times (months)($k)
A 8021040
B 303810
C 402580
D 5021150
E 100415100
F 301620
Total 300

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!