Question: hello i need the answer for this question asap The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a

hello i need the answer for this question asap
hello i need the answer for this question asap
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Activity a m Time Estimates (weeks) b Activity Predecessor 7 3 5 B 4 8 10 A 2 3 3 5 6 12 , COCO E 5 15 D Table 9.2 Reference Ref 9-2 Using Table 9.2, the expected time to complete the project is Select one: O A. 31.00 weeks. O B. 21.67 weeks. O C.34.17 weeks. D. 33.23 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!