Question: Hello I needd help on figuring out number 3 is thise problem? Exercise 9-16 Manufacturing cycle time and efficiency LO A4 Oakwood Company produces maple
Hello I needd help on figuring out number 3 is thise problem?
Exercise 9-16 Manufacturing cycle time and efficiency LO A4
| Oakwood Company produces maple bookcases to customer order. It received an order from a customer to produce 5,000 bookcases. The following information is available for the production of the bookcases. |
| Process time | 9.0 | days |
| Inspection time | 0.7 | days |
| Move time | 3.1 | days |
| Wait time | 17.0 | days |
| Required: | |
| 1. | Compute the companys manufacturing cycle time. (Round your answers to 1 decimal place.) |
| 2. | Compute the companys manufacturing cycle efficiency. (Round your answers to 1 decimal
| ||||||||||||||||||||||