Question: Hello, my answer for this question is 7.75, I would like to know if it is right. Question 10 Not yet answered Marked out of

Hello, my answer for this question is 7.75, I would like to know if it is right.
Question 10 Not yet answered Marked out of 1.00 Flag question The following 4 jobs arrive in sequence to a glass-cutting work center: Job A: Processing time: 3, due date: 4 Job B: Processing time: 13, due date: 4 Job C: Processing time: 1, due date: 17 Job D: Processing time: 9, due date: 7 Calculate the average job lateness if the priority rule is first come first servedStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts