Question: hello , plz solve it using AON Q4. Complete precedence calculation for the activities in the following table. [15 marks] Activity Duration Preceded Type by

hello , plz solve it using AON
Q4. Complete precedence calculation for the activities in the following table. [15 marks] Activity Duration Preceded Type by relationship time 7 .I of Lag K L 5 M 9 FTS 3 STS 6 o FTF 3 N 11 FTS 4 FTS 2 o 12 FTS 1 STS 5 5 K FTF 2 P 12 STS 4 L FTF 2 Q 8 P FTS 0Step by Step Solution