Question: Help Elysian Fields, Inc., uses a maximum payback period of 6 years and currently must choose between two mutually exclusive projects. Project Hydrogen requires an

Help Elysian Fields, Inc., uses a maximum payback period of 6 years and currently must choose between two mutually exclusive projects. Project Hydrogen requires an initial outlay of $29,000: project Helium requires an initial outlay of $34,000. Using the expected cash inflows given for each project in the following table, calculate each project's payback period. Which project meets Elysian's standards? The payback period of project Hydrogen is years. (Round to two decimal places.) con here in order to copy the contents of the data table sheet.) Year 1 2 3 Expected cash inflows Hydrogen Helium $5,000 $8,000 $7,000 $7,500 $7,500 $7,500 $5,000 $6,000 $3,500 $4,000 $2,000 $3,000 4 5 6 Print Done