Question: help Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate (LO2-3) Mickley Company's plantwide predetermined overhead rate
Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate (LO2-3) Mickley Company's plantwide predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $16.00 per hour. The following information pertains to Job A-500: Direct material Direct labor $. 240 $ 160 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. It Job A-500 consists of 50 units, who is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2 Unit product cost per unit