Question: Help how to solve for the Earliest Start Time. Consider the AON graph of a project shown below. The activity times are 2 , 4

Help how to solve for the Earliest Start Time.
Consider the AON graph of a project shown below.
The activity times are 2,4,3,7,8,3,1, and 2 days for activities A1 through A8, respectively.
What is the earliest completion time of the project?
Project time
days