Question: help In the next table are presented the activities, the durations (days) and the relations for the activities of a complex process: Activity Duration Predecessors


help
In the next table are presented the activities, the durations (days) and the relations for the activities of a complex process: Activity Duration Predecessors B 115 E 115 B H 50 E K 30 150 K N Q 175 N T 125 X 175 HQT X Z 95 Compute: The duration of the critical path of the process (the min term of the final node) For activity B ES: EF: LS: For activity E ES: EF: LS: For activity N IS ES For activity E ES: EF: LS: LF: TE: For activity N N ES: EF: LS: LF: TE: For activity T. ES: EF: ILS: LF: ETE: For activity X ES: EF: LS: LF: TFStep by Step Solution