Question: Help me fill out the chart The demand for subassembly S is 80 units in week 7 . Each unit of S requires 2 units
Help me fill out the chart



The demand for subassembly S is 80 units in week 7 . Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 1 unit of V,1 unit of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T, 2 weeks to make U,1 week to make V,3 weeks to make W, 1 week to make X,2 weeks to make Y, and 2 weeks to make Z. Click the icon to view the product structure and the time-phased product structure. In addition to 80 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6 . Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). More Info The time-phased product structure. The demand for subassembly S is 80 units in week 7 . Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 1 unit of V,1 unit of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T, 2 weeks to make U,1 week to make V,3 weeks to make W, 1 week to make X,2 weeks to make Y, and 2 weeks to make Z. Click the icon to view the product structure and the time-phased product structure. In addition to 80 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6 . Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). More Info The time-phased product structure
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts