Question: help needed. can you also show how you got the answer to this please 1,044 inargin of error +1+0,001 Question 11 0/1 pts A future
1,044 inargin of error +1+0,001 Question 11 0/1 pts A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time is 24 weeks, and the project variance is 8 weeks. If the project deadline is set to be51 weeks, then what is the probability that the project would need moge than the given deadline to complete? Input should be either 1 or 2 . with 1 represents "more than 508 and 2 represents "equal or less than 50%. Question 12 0/1pts Several complaints recently have been sont to the LA city office regarding the increasing incidence of congesticn on the city's streets
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts