Question: help please 1. A analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 8.00 minutes, and the stand deviation

help please help please 1. A analyst has timed a
1. A analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 8.00 minutes, and the stand deviation was 1.20 minutes for a worker with a performance rating of 75 percent. Assume an allowance of 9 percent of job time and 12 percent of job day. Find the standard time(s) for both the job and the day of this operation. (10 points each)