Question: help please 1.) What is the normal time for operation?______ (Rounded to two decimal places) 2.) What is the standard time for operation?______(Rounded to two
help please

1.) What is the normal time for operation?______ (Rounded to two decimal places)
2.) What is the standard time for operation?______(Rounded to two decimal places)
Peter Rourke, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. Task Element 1 5 1 Performance Rating 105 % 90 % 80 % 80% 0.5 0.6 0.5 1.6 Observation (minutes per cycle) 2 3 4 0.4 0.6 0.5 0.9 0.7 0.5 0.4 0.8 0.5 1.8 2.1 1.8 2 0.5 0.7 0.5 1.6 3 4 The allowances for tasks such as this are personal, 7%; fatigue, 8%; and delay, 3%Step by Step Solution