Question: Help Please! Answer all questions if possible! You are one of five carpenters assigned to complete a short construction project. Right before the start of

You are one of five carpenters assigned to complete a short construction project. Right before the start of the project, one of your fellow carpenters is hospitalized and will not be available to work on the project. Develop a resource-constrained schedule to see how long the project will take with only 4 carpenters. Be sure to record the order in which you schedule the activities usingnthe scheduling heuristics. The number of carpenters required for each activity is as shown in the diagram. No splitting of activities is possible. You will receive a bonus if the project is completed within 19 days. What is the resource-constrained length of the project? Can you expect a bonus