Question: Help please! Develop MRP records for all items needed for item F in the following product structure for product H, using the information provided in
Help please!
Develop MRP records for all items needed for item F in the following product structure for product H, using the information provided in the following tables. The lead time to complete product H is one week. Master production schedule (MPS) calls for 190, 130, and 90 units of demand for period 4, 5, and 6.
| Planning Data | |||||
| Data Category | D | E | F | G | I |
| Lot size rule | Q= 15* | L4L | L4L | Q=300* | L4L |
| Lead time | 2 weeks | 1 week | 1 week | 2 weeks | 2 weeks |
| Safety stock | 15** | 25 | 20 | 35 | 0 |
| Scheduled receipts | None | none | 1,300 (wk 1) | 700 (wk 1) | 900 (wk 1) |
| Beginning inventory | 30 | 40 | 20 | 50 | 0 |
*Planned order schedules must be the same or multiples of Q amount **minimum on hand (ending inventory) quantity to be observed FORMAT FOR ENTRIES: All quantities are INTEGER, Enter 0 if you do not have quantity for any period. PROVIDE THE FOLLOWING SELECTED VALUES:
| Planned Order Release Quantities for Product H | ||||
| Period 1 | Period 2 | Period 3 | Period 4 | Period 5 |
|
|
|
|
|
|
| Gross Requirements Quantities for Item F | ||||
| Period 1 | Period 2 | Period 3 | Period 4 | Period 5 |
|
|
|
|
|
|