Question: help please!! // operations management An assembly line with 60 activities is to be balanced. The total amount of time to complete all 60 activities
An assembly line with 60 activities is to be balanced. The total amount of time to complete all 60 activities is 40 minutes. The longest activity takes 3.0 minutes and the shortest takes 0.4 minute. The line will operate for 600 minutes per day. a. What are the maximum and minimum cycle times? Round your answers to one decimal place. Maximum cycle time: minutes Minimum cycle time: minutes b. How much dally output will be achieved by each of those cycle times? Round your answers to the nearest whole number. Daily output achieved by maximum cycle time: units/day Daily output achieved by minimum cycle time: (3) units/day