Question: HELP please Question 12 What is the planned order release quantity for Week 2 for the MRP data shown below? Part XYZ Gross Requirements Scheduled

HELP please

HELP please Question 12 What is the planned order

Question 12 What is the planned order release quantity for Week 2 for the MRP data shown below? Part XYZ Gross Requirements Scheduled Receipts Projected Balance Planned Order Receipts Planned Order Releases Q = 60, LT= 3 weeks, Safety Stock = 5 O 120 units O0 unit O 60 units O Insufficient information to compute the answer O 65 units 120 Week 1 Week 2 80 0 60 Week 3 90 Week 4 0 Week 5 70 W