Question: help, please Using the replacement chain (common-life) approach, can you type the net present value of the project you would choose (A or B)? .....
Using the replacement chain (common-life) approach, can you type the net present value of the project you would choose (A or B)? ..... Assume the discount rate is 5%. Year 0 Project A -165,912 54,023 43,097 48,706 55,291 Project B -63,287 42,520 40,939 1 2 3 A *Round your answer to the nearest two decimals if needed. Do not type the $ symbol