Question: help please!! What provides feedback to the capacity plan, master production schedule, and production plan so planning can be kept valid at all times? A.
help please!!
What provides feedback to the capacity plan, master production schedule, and production plan so planning can be kept valid at all times? A. closed-loop MRP system B. MRPII C. lot sizing D. system nervousness