Question: help pls (2) You are evaluating a project with the following expected cash flows: an initial investment of $11 million, followed by cash flows of
You are evaluating a project with the following expected cash flows: an initial investment of $11 million, followed by cash flows of $5,$10 and $21 million in years 1,2 and 3 , respectively. If the company's discount rate is 17%, what is this projects NPV? Enter your answer in millions of dollars, with no decimals. For example, if your answer is $12,345,678.90, you should enter 12