Question: Help populate this with at least ten risks for migration to a cloud-based email in a small college. ID Risk Name Risk Description Impact Probability

Help populate this with at least ten risks for migration to a cloud-based email in a small college.

ID Risk Name Risk Description Impact Probability Risk Ranking Positive/Negative Proactive Response Plan Trigger Event Reactive Contingency Plan
VH,H,M,L,VL VH,H,M,L,VL What is the risk color code ? Is this a positive or negative risk from the risk matrix? What proactively can be attempted to make the risk happen or prevent it? What do you think will trigger the event? What are your backup plans if the risk should occur?
1 Example: please remove before completing document. Critical equipment does not arrive on time. If critical pieces of equipment do not arrive on time, the project will fall behind schedule. H H Red Negative 1. Add activities to the WBS to ensure with the manufacturer that the equipment is being built or shipped as required. 2. Have a member of project team go to the manufacturing plant to ensure equipment parts are in progress and on schedule. 3. Add steps to the WBS to ensure the manufacturer ships on time. 4. Add steps to WBS to track the shipment as needed. Parts do not ship on assigned date. If possible, have a backup supplier identified and standing by.
2
3
4
Risk Matrix
Very high
High
Medium
Impact Low
Very low
Very low Low Medium High Very high
Probability
Risk Matrix

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!