Question: Help Save&Exit S 2 ng March, the company worked 26,000 machine-hours and produced 15,000 units. The company had originally planned to work 30,000 machine-hours during
Help Save&Exit S 2 ng March, the company worked 26,000 machine-hours and produced 15,000 units. The company had originally planned to work 30,000 machine-hours during March. Required: 1. Calculate the activity variances for March. 2. Calculate the spending variances for March points Complete this question by entering your answers in the tabs below. Required 1 Required 2 Print Calculate the activity variances for March. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) References Activity Variances th Ended March 31 Utiies Supplies Indirect labor Total Required 2