Question: help solving question 16 and 17 Question 16 (5 points) Saved Calculate the direct cost of labor for a project team member using the following

help solving question 16 and 17 help solving question 16 and 17 Question 16 (5
Question 16 (5 points) Saved Calculate the direct cost of labor for a project team member using the following data: 1. Hourly rate: $44.00 per hour 2. Hours needed: 94 3. Overhead rate: 45% Your Answer: 4,136 Answer Question 17 (5 points) Saved Mrs. Tolstoy and her husband, Serge, are planning their dream house. The lot for the house sits high on a hill with a beautiful view of the Appalachian Mountains. The plans for the house show the size of the house to be 2,800 square feet. The average price for a lot and house similar to this one has been $135 per square foot. What can they expect the house to cost? Your Answer: 378,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!